Bulk Material Requirement for General Building Construction Work

Material Coefficient per Built Up Area

Sand can be taken as 1.8 Cft /Sft
CA can be taken as 1.4 Cft / Sft
Cement can be taken as 0.5 bags /sft
Steel can be taken as 3.5 kgs /Sft
Bricks can be taken as 10 Nos / Sft