Top softwares used by civil engineers
Civil Engineering PE Practice Exams
02 September 2018
22 April 2018
Cost Engineering
Cost engineering
the engineering practice devoted to the management of
project cost, involving such activities as estimating, cost control, cost
forecasting, investment appraisal and risk analysis. Cost Engineers
budget, plan and monitor investment projects. They seek the optimum balance
between cost, quality and time requirements.
Skills
and knowledge of cost engineers are similar to those of quantity surveyors. In
many industries, cost engineering is synonymous with project controls.
A cost engineer is "an
engineer whose judgment and experience are utilized in the application of scientific
principles and techniques to problems of estimation; cost control; business
planning and management science; profitability analysis; project management;
and planning and scheduling.
One key
objective of cost engineering is to arrive at accurate cost estimates and
schedules and to avoid cost overruns and schedule slips. Cost engineering goes beyond
preparing cost estimates and schedules by helping manage resources and
supporting assessment and decision making. The discipline of ‘cost engineering’
can be considered to encompass a wide range of cost-related aspects of
engineering and programme management, but in particular cost estimating, cost
analysis/cost assessment, design-to-cost, schedule analysis/planning and risk assessment. The
broad array of cost engineering topics represent the intersection of the fields
of project management, business management, and engineering. Most people have a
limited view of what engineering encompasses.
The most obvious perception is that engineering addresses technical issues such
as the physical design of a structure or system. However, beyond the physical
manifestation of a design of a structure or system (for example, a building),
there are other dimensions to consider such as the money, time, and other
resources that were invested in the creation of the building. Cost engineers
refer to these investments collectively as "costs".
HISTORY
Cost engineering is a field of
engineering practice that began in the 1950s (AACE International was founded in
1956). The skills and knowledge areas of cost engineers are similar to those
of quantity surveyors. AACE International is one of many international
engineering organizations representing practitioners in these fields. The
International Cost Engineering Congress (ICEC) was founded in 1976 as a
Worldwide Confederation of Cost Engineering, Quantity Surveying and Project
Management Societies.
In
2006, AACE published the Total Cost
Management (TCM) Framework which outlines an integrated process for
applying the skills and knowledge of cost engineering (see References). This
has also been called the world's first process for portfolio, program and
project management.
Roles & Responsibilities of Quantity Surveyor
A Quantity Surveyor (QS) is
a construction industry professional with expert knowledge on
construction costs and contracts does the following jobs
·
Cost consulting, cost estimating
·
Cost planning and commercial management throughout the entire
life cycle of the project from inception to post-completion
·
Value determination
·
Risk management and calculation
·
Procurement advice and assistance during the tendering procedures
·
Tender analysis and agreement of the contract sum
·
Preparation of pricing documents (e.g. Bills of Quantities) in tender
·
Drafting contract conditions and contractual correspondence
·
Commercial management and contract administration
·
Contractual advice
·
Assistance in dispute resolution
·
Asset capitalisation
·
Interim valuations and payment assessment
·
Cost management process
·
Assessing the additional costs of design variations
·
Production of company pre-qualification questionnaire (PQQ)
documentation in line with company policies
·
Project management
·
Assist in establishing a client's requirements
Roles & Responsibilites
1. Cost estimating
2. Cost planning
3. Cost studies
4. Cost monitoring and
controlling
5. Measurement
6. Contracts
negotiation
7. Drafting contract
conditions
8. Procurement advice
including tendering strategy
9. Preparing Bill
of Quantities (BOQ) and Tender Document
10. Contract practice
11. Valuation of
construction work including variations
12. Assessment of
contractor’s claims
13. Contractual advice
14. Dispute resolution
15. Preparing
feasibility studies
16. Advice on cost
limits and budgets
17. Whole life cycle
costing
18. Valuation for
insurance purposes
19. Project management
20. Advice on
contractual disputes
21. Preparation of
final account
22. Preparation of
final detailed BOQ
IS-1200 =Methods of measurement of building and civil engineering works,
- IS-1200 PART-1 - EARTHWORKS
- IS-1200 PART-2 - CONCRETE WORKS
- IS-1200 PART-3 - BRICK WORK
- IS-1200 PART-4 -STONE MASONRY
- IS-1200 PART-5 - FORMWORK
- IS-1200 PART-6 REFRACTORY WORKS
- IS-1200 PART-7 - HARDWARE
- IS-1200 PART-8 - STEEL & IRON WORKS
- IS-1200 PART-9 - ROOF COVERING WORKS
- IS-1200 PART-10 - CEILING & LINING WORKS
- IS-1200 PART-11 - FLOORING & DADO WORKS
- IS-1200 PART-12 - PLASTERING & POINTING WORKS
- IS 1200 (Part 13) : 1994 - WHITE WASHING, COLOUR WASHING, DISTEMPERING AND PAINTING OF BUILDING SURFACES
- IS1200 PART-14 - GLAZING WORKS
- IS1200 PART-15 - PAINTING & POLISHING
- IS1200 PART-16 - WATER & SEWER LINES
- IS1200 PART-17 - road work including air field pavements
- IS1200 PART-18 - demolition and dismantling
- IS1200 PART-19 - Water Supply, Plumbing and Drains
- IS1200 PART-20 - laying of gas and oil pipelines
- IS1200 PART-21 - wood-work and joinery
- IS1200 PART-22 - materials
- IS1200 PART-23 - piling
- IS1200 PART-24 - well foundations
- Steel Tables
Complied by My Student Irfan 9494717554
26 January 2018
Subscribe to:
Posts (Atom)